A30 Chiverton Cross

Project Overview

Topan Group recently undertook the permanent fencing on the A30 Chiverton Cross to Carland project, valued at £3 million, which involved installing over 44 kilometres of diverse fencing and gate solutions. The extensive scope of work, completed in December 2025 for client Costain, included a range of critical installations. The success of this project was the result of smart design, a joined-up approach, and a collaborative problem-solving attitude with Costain.

 Scope of the work

The works ranged from 29 kilometres of HCD H3 post and four rail fencing with buried badger netting to 4 kilometres of HCD H12 stockproof fencing.

The project also featured unique elements like:

  • 1,355 meters of light diffusion fencing
  • 630 meters of 3-meter-high timber acoustic fencing
  • 250m of HCD H14 timber featheredge fencing
  • 50 HCD steel field gates
  • 79 badger-proof gates
  • 77 badger access flaps

The Solution

A good working partnership with Topan, Costain, the designer Jacobs, and National Highways enabled a significant breakthrough. The switch to pointed and driven timber posts for the badger fencing delivered substantial cost savings and shortened the overall project timeline. Additionally, the team switched from a chain-link to a hinged-joint system, enabling a buried lap.

The acoustic fencing required a bespoke approach to post design and wind loading. Also, a hybrid light diffusion and badger fence was designed with specific gaps to account for site-specific wind loading.

The Outcome

Significant time and cost savings were achieved with the badger fencing due to the use of driven posts combined with the hinged badger net.

The extraordinary coastal wind loadings led Topan’s engineers to devise a clever solution for the HCD H14 fencing, using longer, non-morticed posts with shorter centres to achieve the required strength without exceeding the client’s budget.